So far, we have discussed the different levels of detail of the production planning individually, but in practice, it requires integration across these different levels, from high-level aggregate plans to the detailed scheduling.
This section addresses how these levels interact and how to handle changes.
Aggregate demand (if original demand is defined at that level) is disaggregated into specific SKUs and distributed across weeks/months.
Good forecast accuracy at the lowest level is needed as it ensures that the MPS is realistic and actionable, avoiding overproduction or resource underutilization.
Weekly SKU targets drive material requirements. The BOM ensures accurate raw material planning for each product type.
Timely updates to the BOM and lead times in the system of record are crucial. For instance, any delay in binding agent procurement impacts production schedules downstream.
Material availability dictates the feasibility of daily/hourly task assignments in detailed schedules.
Impact: adjustments required in the MPS, MRP, and Detailed Scheduling.
Actions: update MPS to include the new order. Need to Run MRP again to adjust material procurement/manufacturing. Re-sequence detailed schedules, potentially delaying lower-priority tasks
Actions: adjust the detailed schedule, assuming the breakdown is only for a short duration. Then communicate changes upstream to revise the MRP and potentially the MPS if needed.
1. Frozen zone (detailed scheduling):
This covers the first few days to a few weeks, depending on the industry and lead times.
Plans are fixed and require significant approval for changes since changes in this period can disrupt operations, increase costs, and lead to inefficiencies.
2. Slushy zone (master production schedule control):
Begins after the frozen zone and extends up to the cumulative lead time for production and material procurement.
Limited flexibility; changes are possible but require approval and coordination.
3. Liquid zone (planning system suggestions):
Covers the horizon beyond the cumulative lead time, typically up to 12 months.
High flexibility; plans are dynamically generated by planning systems based on forecasts. Used for long-term resource planning and capacity leveling.
The focus is on aligning the plan with sales and operations planning (S&OP) goals.
Frozen zone: detailed schedulers and operations teams are responsible for execution.
Slushy zone: master schedulers take ownership of adjustments and feasibility checks. This article dives deeper into the slushy zone.
Liquid zone: long-term planners and demand planners ensure alignment with strategic goals.